CO₂ Bottling · Solar (Corrected) · Heat Recovery · ETP Innovations · Portfolio ROI
DPR v15 · Sept 2026
DISCOM constraint — 400 kWp is the hard ceiling: TSERC net metering rules cap solar installation at 80% of sanctioned load. Sanctioned load = 500 kW → max solar panel installation = 400 kWp. This is the regulatory limit, not an economic choice. DPR already has 250 kWp; incremental = +150 kWp to reach the 400 kWp cap.
Solar PV — 400 kWp Maximum (150 kWp incremental from DPR 250 kWp)
Sangareddy: 5.5–6.0 kWh/m²/day · DISCOM cap: 80% × 500 kW sanction = 400 kWp max installation
₹1.20 Cr
Total 400 kWp capex
₹0.13 Cr
Incremental saving/yr (+150 kWp)
2.4 yr
Payback (post-subsidy)
₹0.35 Cr
Total saving/yr at 400 kWp
400 kWp Installation Cap — Derating to Effective Output
Derating FactorLoss %Effective kW
Panel rated output (DISCOM cap)400 kWp
Temperature derating (40-45°C ambient)−8%368 kW
Soiling + shading−3%357 kW
Inverter efficiency−3%346 kW
Cable + transformer losses−2%~339 kW
400 kWp installed → ~339 kW effective peak output. Covers 75% of operating load (454 kW) during peak sunshine (~6 hrs/day), displacing ~22% of 24-hour grid draw.
System ComponentCost (400 kWp)
Panels (Tata Solar / Waaree, 400 kWp)₹56L
String inverters (SolarEdge / SMA)₹20L
MS structure + cable trays₹15L
AC/DC cables + protection₹10L
Net meter + TSERC compliance₹8L
Civil (ground mount foundation)₹8L
EPC margin + commissioning₹3L
TOTAL (400 kWp)₹1.20 Cr
Incremental Economics (Beyond Existing DPR 250 kWp, up to DISCOM cap)
Existing (DPR)
250 kWp already in DPR
315,000 kWh/yr
₹0.22 Cr/yr saving
~₹75L capex (in DPR utilities bundle)
Incremental (to DISCOM cap)
+150 kWp to reach 400 kWp total
+189,000 kWh/yr additional
+₹0.13 Cr/yr saving
₹0.45 Cr capex (₹1.20 − ₹0.75)
Payback: 3.4 yr gross
Post TSREDCO Subsidy (30%)
TSREDCO + PM-KUSUM Component C
30% on ₹0.45 Cr = ₹13.5L subsidy
Net capex: ₹0.32 Cr
Payback: 2.4 yr ✓
Hard ceiling at 400 kWp: DISCOM will not approve solar net metering beyond 80% of your 500 kW sanctioned load — this is the regulatory limit, not an economic one. To go beyond 400 kWp you would need a load enhancement application to DISCOM (possible at Phase 1B/Phase 2 when installed load increases to 600–700 kW). At that point, the new 80% cap would be 480–560 kWp. Revisit this at Month 18 alongside Phase 1B sanction enhancement.
CO₂ Bottling Plant — 1.5 MT/day Industrial Grade
10% of 15.69 MT/day surplus · MEA absorption · Stripper heat from THU surplus (zero cost)
₹1.50 Cr
Capex
₹0.59 Cr
Revenue/yr
₹0.46 Cr
EBITDA/yr
3.2 yr
Payback
CO₂ Mass Balance — Where the Carbon Goes
Rice husk combustion
25.05 MT/day CO₂
Gross CO₂ produced
PCC precipitation
9.36 MT/day
Used in process (5% excess)
Surplus (currently vented)
15.69 MT/day
5,178 MT/yr to atmosphere
Capture 10%
1.5 MT/day
495 MT/yr bottled
Remaining surplus
14.19 MT/day
BCR credits potential (Y3+)
Process Flow
1. Flue gas cyclone
Remove fly ash + particulates
Already required for
TSPCB compliance
2. NaOH scrubber
Remove SOx to <10 ppm
Already planned for
flue gas cleaning (₹8-15L)
3. MEA absorption column
85-90% CO₂ capture into amine solution
₹50L (local fab)
4. MEA stripper (heated)
Release CO₂ · heat from THU surplus
ZERO fuel cost
4.5 GJ/day from surplus
5. 3-stage compressor
Compress to 60 bar · Kirloskar/ELGi
₹30L · 15 kW avg power
6. Drying + liquefaction
Molecular sieves → −20°C liquid CO₂
₹10L dryer · integrated
with compressor last stage
7. Storage + filling
10 MT insulated tank · cylinder manifold
₹40L · 1 operator
Capex Breakdown
Item₹ LakhsNote
MEA absorption + stripping (local fab SS316)50BHEL/Praj local fabricator
CO₂ compressor 3-stage (Kirloskar)30Made in India · spares local
Molecular sieve dryer10Standard skid
Liquid CO₂ storage (10 MT insulated)25Vacuum insulated vessel
Cylinder filling station + manifold1550 cylinders capacity
Civil + piping + E&I + SCADA20Adjacent to furnace
TOTAL CAPEX150= ₹1.50 Cr
Annual Economics
Item₹ Cr/yr
Revenue: 495 MT/yr × ₹12/kg industrial CO₂+₹0.59
Welding gas: ₹12–15/kg · Fire suppression: ₹15–18/kg
MEA solvent makeup + chemicals−₹0.04
Electricity (compressor ~15 kW avg)−₹0.02
1 additional operator (₹3.5L CTC)−₹0.04
Maintenance−₹0.03
Stripper heat (4.5 GJ/day from THU surplus)₹0.00 cost
EBITDA₹0.46 Cr/yr
EBITDA MARGIN
78%
PAYBACK
3.2 yr
Key advantage: The MEA stripper requires heat at ~120°C — this comes from the THU thermal oil circuit (83 GJ/day surplus). Needs only 4.5 GJ/day (5.4% of surplus). This is the only industrial CO₂ capture setup in India where stripping heat is free. Most competitors pay ₹800–1,200/GJ for this heat; Fluxara pays zero.

Y2 upgrade path: Once industrial CO₂ offtake is established, upgrade purification to food-grade (CO₂ purity 99.99%, add activated carbon + molecular sieve column, ₹15L additional). Food-grade CO₂ prices: ₹28–38/kg vs ₹12/kg industrial — EBITDA rises to ₹1.0+ Cr/yr with same capex base.
Prerequisite: Lock an offtake buyer before ordering the MEA column. Target: Air Liquide India / Inox Air Products / regional welding gas distributors in Hyderabad (Patancheru / Balanagar belt). They often prefer to operate the bottling themselves — negotiate a tolling model where they install the compressor/storage at their cost and pay you ₹7–9/kg for CO₂ at the plant gate. Lower your capex to ₹65–70L (just absorption + cyclone); their ROI is fine at ₹3–5/kg margin.
Heat Integration & Recovery Matrix
THU thermal oil circuit · 83 GJ/day surplus in Y1 · 74 GJ/day post Phase 1B
₹50L
Total capex (excl. causticiser)
₹1.19 Cr
Total saving/yr
0.4 yr
Blended payback
0.47
₹/1% NaOH recovery
Thermal Surplus Map — Where the Energy Actually Goes
HEAT AVAILABLE
Rice husk NCV (20 MT/day)
243.0 GJ/day gross
After boiler losses (82% eff.)
199.3 GJ/day useful
CaO slaking exotherm
15.2 GJ/day @ 80-100°C
Spray dryer exhaust
6.5 GJ/day @ 65-95°C
HEAT CONSUMED
Evaporation (with MVR)
58.5 GJ/day
NaOH leaching @ 90°C
42.7 GJ/day
Spray drying
15.1 GJ/day
CO₂ stripper (if built)
4.5 GJ/day
Phase 1B (Month 18)
9.0 GJ/day
SURPLUS (RECOVERABLE)
Y1 thermal surplus
83.0 GJ/day
After CO₂ stripper
78.5 GJ/day
After Phase 1B (Month 18)
69.5 GJ/day
Phase 2 anchor
~69 GJ/day remaining
Heat Recovery Projects — Ranked by ROI
★ Draft-Tube Causticiser (CHAMPION ROI)
Capex₹30–35L
NaOH recovery82% → 86–88%
NaOH saving/yr₹0.94–1.88 Cr
PCC quality upliftd50 0.5–0.8 µm → sealant grade direct
Payback<0.4 years
How it works: Dorr-Oliver draft-tube design creates controlled turbulence in causticisation vessel → better Ca(OH)₂–Na₂CO₃ contact → 86–88% conversion vs 82% in standard tank. Finer CaCO₃ crystals (0.5–0.8 µm d50) are sealant grade directly without post-processing. Install at commissioning — not a retrofit.
CaO Slaking Exotherm Recovery
Capex₹10–12L
Heat available15.2 GJ/day @ 80-100°C
Recovery (30%)4.6 GJ/day
THU load reduction~4%
Saving/yr₹0.15 Cr
Payback0.8 yr
How it works: Slaker discharge (Ca(OH)₂ slurry at 80–100°C) passes through a plate heat exchanger before entering the causticiser. Pre-heats NaOH leach feed water from ambient to 60°C, cutting THU load on leach circuit. Equipment: one SS316 gasketed plate HX from Alfa Laval India. Zero moving parts. Sangareddy summers make this particularly valuable (ambient 40–45°C reduces temperature lift needed).
Spray Dryer Exhaust WHR Recuperator
Capex₹8L
Exhaust temp65–95°C
Heat recovered6.5 GJ/day
UsePre-heat incoming drying air
Saving/yr₹0.10 Cr
Payback0.8 yr
How it works: Air-to-air rotary heat exchanger (recuperator) on spray dryer exhaust duct. Pre-heats incoming ambient air from ~40°C to ~70°C before entering the spray dryer inlet heater. Reduces THU heat load on spray dryers by 6–8%. SS316 recuperator from Heatex India or local fab. Simple retrofit, no process change.
MVR on Evaporator (DPR Mandatory)
Capex₹150L (in DPR)
Without MVR167.1 GJ/day evap load
With MVR58.5 GJ/day (−65%)
Heat saved108.6 GJ/day
Without MVR25.6 GJ/day deficit → plant stops
StatusAlready in DPR · Non-negotiable
This is not optional. Without MVR, thermal deficit = 25.6 GJ/day and plant cannot operate at design throughput. Already included in ₹150L triple-effect evaporator line item. Also enables the 83 GJ/day thermal surplus that makes Phase 2 and CO₂ plant viable.
ZLD MVR (Included in ETP+ZLD)
CapexIncluded in ₹120L ZLD
ZLD water recovery80%
ZLD electricity~8 kWh/m³ treated
Fresh water makeup84 KLD (Ph1A)
StatusIn DPR from Day 1
ZLD MVR compresses the vapour from the first evaporation stage to heat the second stage — same principle as process MVR. Reduces ZLD electricity from ~25 kWh/m³ (multi-effect without MVR) to ~8 kWh/m³. Already designed into the ETP+ZLD ₹120L capex.
ORC Electricity Generation (Phase 2 / Y3+)
Available surplus (post Ph1B)~69 GJ/day
ORC efficiency10–12% (at 150–180°C)
Power potential~800–1,000 kW
Revenue/yr₹1.8–2.2 Cr/yr (grid export)
ORC capex₹8–12 Cr
Payback4–6 yr (not Y1/Y2)
Not recommended for Y1–Y2. ORC at this scale costs ₹8–12 Cr (Turboden/Exergy Europe). Revenue only ₹1.8–2.2 Cr/yr on a ₹10 Cr investment = 4–6 yr payback. Defer to Y3 or Phase 2 once capital is freed. Better use of the thermal surplus: add a second production line (Phase 2) which turns heat into ₹20+ Cr revenue, not ₹2 Cr in electricity.
ETP / ZLD Innovations — Sangareddy Conditions
Semi-arid climate · 2,000 mm/yr evaporation · 5 acre land (3 TSIIC + 2 buffer) · 84 KLD fresh water input
₹27L
Total capex
₹0.13 Cr
Annual benefit
2.1 yr
Blended payback
80%
ZLD water recovery
ETP Water Balance — How 84 KLD Moves Through the Plant
Fresh water intake
84 KLD
Groundwater + TSIIC supply
Process use
84 KLD
Leaching · causticisation · spray drying
ETP treatment
~100 KLD
pH adj · coagulation · clarification
ZLD evaporation
80% recovery
67 KLD recycled back to process
ZLD concentrate
~17 KLD
To evaporator → salt cake
Solar Evaporation Pond
What: 0.25 acre HDPE-lined evaporation pond receives ZLD concentrate (17 KLD) before the MVR evaporator. Sangareddy has 2,000 mm/yr evaporation rate — the pond evaporates 3–5 KLD naturally, reducing MVR evaporator duty by 20–30%.

Capex: ₹5L (HDPE liner 400 gsm + earthwork + inlet pipe)
Saving: Reduces ZLD electricity 15–20% = ₹3–4L/yr on power bills
Monsoon management: Install a polyethylene roof cover or seasonal bypass during Jun–Sep (Sangareddy: 700–900 mm monsoon). This pond is the cheapest KLD of treatment in the entire plant.

Also captures: Sodium compounds in concentrate begin crystallising → reduces scaling in the MVR evaporator (extends cleaning intervals from 6-monthly to annual).
ETP Polished Water — Fish Pond
What: ZLD polished water (pH 7.5–8.5, BOD <5 mg/L, TSS <10 mg/L) is suitable for freshwater aquaculture. 0.5 acre pond fed from ETP tertiary treated water. Stock catla, rohu, and tilapia (all Telangana-native, fast-growing, high local demand).

Capex: ₹7L (pond excavation + HDPE liner + fingerling stock + net)
Yield: 2–2.5 MT fish/yr at 2,000 fingerlings/0.5 acre stocking density
Revenue: ₹130/kg at local Sangareddy fish market = ₹2.6–3.2L/yr

Dual benefit: (1) Revenue, (2) TSPCB inspector goodwill — demonstrating beneficial use of treated water is excellent for CTO renewal. Sangareddy fishing community may also be interested in a lease arrangement (they manage it, you get ₹1L/yr ground rent).
ZLD Salt Cake Partial Recovery
What: ZLD evaporator produces a mixed salt cake. The Fluxara process generates primarily sodium carbonate (Na₂CO₃) and calcium carbonate (CaCO₃) in the concentrate. A simple crystallisation step on a side-stream can separate a partial Na₂CO₃ fraction.

Capex: ₹15L (crystallisation vessel + centrifuge, small-scale)
Yield: 30–40 MT/yr Na₂CO₃ partial-grade (not reagent-pure, but suitable for wastewater treatment or tile manufacturing)
Revenue: ₹10,000/MT = ₹3.5–4L/yr
Benefit: Also reduces hazardous waste disposal cost (ZLD salt cake classified as industrial waste needing approved disposal = ₹3,000–8,000/MT disposal fee). Every tonne recovered is ₹10K earned + ₹5K disposal avoided.

Alternative: License the salt cake to a cement manufacturer (CaCO₃-rich ash can substitute 5–10% of limestone in clinker) at ₹500–1,000/MT gate. No processing needed. ₹1.5–3L/yr, zero capex.
ETP Design for Sangareddy Conditions — Key Specifications
Climate Adaptations
  • Design ETP for 45°C summer peak — polymer doses shift with temperature
  • Monsoon (Jun–Sep): ETP flow doubles from storm run-off — size clarifier for 2× peak
  • RCC sump (not HDPE tank) for main equalization — cheaper and permanent at this scale
  • Use local lime (CaO from Nalgonda) for pH neutralisation — ₹6,000/MT vs proprietary pH chemicals ₹25,000+/MT
TSPCB Compliance Focus
  • ZLD mandatory from Day 1 (TSPCB condition for process plant in this category)
  • Online pH + TSS sensor to TSPCB portal (auto-log, required for CTO)
  • Fish pond acts as informal bio-indicator — TSPCB inspectors respond positively
  • Monthly self-monitoring lab report to TSPCB as required by consent conditions
Water Cost Optimisation
  • Bore well + TSIIC supply dual feed — bore is ₹3–5/KL vs TSIIC ₹40–60/KL
  • 84 KLD makeup × ₹5/KL bore rate = ₹1.5L/yr vs ₹18.5L/yr TSIIC water — saves ₹17L/yr
  • ZLD 80% recovery means only 84 KLD fresh needed for 420 KLD total process water
  • Groundwater NOC from CGWB — apply through TS-iPASS single window
Total Add-On Capex
₹2.64 Cr
All 5 projects (solar corrected)
Total Add-On EBITDA
₹1.91 Cr/yr
When all fully operational
Blended Payback
1.4 yr
Portfolio-weighted average
Funding Source
Y1–Y2 accruals
Zero additional bank debt
Portfolio Summary — All Capital Projects Ranked by Payback
Project Capex EBITDA/yr Payback Payback Visual Fund From Priority
▶ COMMISSION DAY 1 — Install at build, no additional fundraising
Draft-tube causticiser
NaOH 82%→87% + sealant PCC direct
₹0.35 Cr ₹0.94 Cr 0.4 yr 0.4yr Add to commissioning budget P1 · NOW
CaO slaking HX + spray dryer WHR
Plate HX + recuperator
₹0.20 Cr ₹0.25 Cr 0.8 yr 0.8yr Commissioning budget P1 · NOW
ETP fish pond + solar evap pond + salt recovery
3 small ETP innovations
₹0.27 Cr ₹0.13 Cr 2.1 yr 2.1yr Y1 minor capex P2 · Y1
▶ FROM Y1 ACCRUALS — After Phase 1B (₹1.50 Cr) is funded
Solar 400 kWp total (DISCOM cap)
+150 kWp incremental · TSREDCO 30% subsidy · 80% of 500 kW sanction
₹0.32 Cr net ₹0.13 Cr 2.4 yr 2.4yr Y1 end / Y2 early P2 · Y1-Y2
CO₂ bottling plant (1.5 MT/day)
MEA absorption · THU surplus heat · industrial grade
₹1.50 Cr ₹0.46 Cr 3.2 yr 3.2yr Y2 accruals (after Ph1B) P3 · Y2
▶ REFERENCE — Already in DPR (not additional capex)
MVR on process evaporator
Mandatory · in DPR ₹150L
₹1.50 Cr (DPR) ₹3.30 Cr 0.5 yr DPR Bank term loan MANDATORY
Solar 250 kWp existing
Already in DPR utilities bundle
~₹0.75 Cr (DPR) ₹0.22 Cr 3.4 yr DPR Bank term loan IN DPR
TOTAL Add-On Projects (P1–P3, solar corrected) ₹2.64 Cr ₹1.91 Cr/yr 1.4 yr avg Y1–Y2 accruals only
Funding Waterfall — Y1 Accruals (Full Optimisation Scenario)
Y1 Cash Available (Full Optimisation)
EBITDA+₹5.04 Cr
Less: interest (moratorium)−₹2.11 Cr
Y1 net cash+₹2.93 Cr
T-IDEA SGST rebate (Y1–Y5)+₹1.26 Cr
Total Y1 deployable cash+₹4.19 Cr
Y1 Cash Allocation Priority
#1 Phase 1B (non-negotiable)₹1.50 Cr
#2 Heat integration (Day 1 capex)₹0.20 Cr
#3 ETP innovations₹0.27 Cr
#4 Solar incremental (+ subsidy)₹0.52 Cr
Total deployed from Y1₹2.49 Cr
Remaining for CO₂ plant (Y2)₹1.70 Cr
The sequencing logic: Draft-tube causticiser (₹35L, 0.4 yr payback) is the highest-priority addition — install at commissioning, not as a retrofit. Heat integration pays back in <1 year. CO₂ plant (₹1.50 Cr) waits for Y2 once Phase 1B revenue is established, and ideally use the tolling model (₹65L capex vs ₹1.50 Cr) to get CO₂ revenue stream running earlier with less risk.