Master Financial Model · Precipitated Silica & Nano-PCC Biorefinery · Sangareddy
Last calc: DPR v16 · Sept 2026
Revenue (at util%)
OPEX (at util%)
EBITDA
DSCR (moratorium Y1)
Net Cash (Y1)
Break-even Util%
At current assumptions
P&L Summary — Current Assumptions
Line₹ Cr/yrvs DPR v16 base
Revenue
Variable OPEX
Fixed OPEX₹3.72 Cr
Total OPEX
EBITDA
Interest (moratorium)
Net Cash (Y1)
Key Operational Metrics
MetricValue
NaOH recovery rate
NaOH makeup / day (48% lye)
NaOH cost / MT RHA
PS output at current util
PCC output at current util
Contribution / MT RHA
Break-even PS price
Blended PS price
Blended PCC price
Year-by-Year P&L (standard grade pricing throughout — floor scenario)
YearUtil%RevenueOPEXEBITDAEBITDA%DSDSCRNet Cash
* Y1 moratorium: DS = interest only (₹1.30 Cr at ₹12.43 Cr debt). Y2+ DS = ₹2.66 Cr/yr. Phase 1B revenue from Y2 onward (75% util, 19.60 MT/day RHA). DPR v16: TPC ₹19.13 Cr · Debt ₹12.43 Cr · Equity ₹6.70 Cr. Export pricing throughout.
Variable OPEX — Per Line Item (at 100% Phase 1A)
ItemQty/yr (MT)Price₹ Cr/yrDPR v15Δ
NaOH 48% lye₹5.49 Cr (v15/v16)
Rice husk6,600 MT₹3.63 Cr (v15/v16)
CaO quicklime4,410 MT₹2.65 Cr (v15/v16)
CTAB95.4 MT₹1.72 Cr (HDS only)
Stearic acid53.5 MT₹0.64 Cr (sealant only)
Purchased RHA3,773 MT₹0.28 Cr (v15/v16)
Packing + transport₹1.20₹1.20 Cr₹0
Electricity (variable)₹0.49₹0.49 Cr₹0
Variable subtotal (100%)₹13.74 Cr (v16 base)
Fixed OPEX (does not scale with utilisation)
Item₹ Cr/yr
Electricity (base grid load)₹1.00
Labour (25 staff avg ₹4.8L CTC)₹1.20
Maintenance (2% of fixed assets)₹0.65
Admin + insurance + other₹0.87
Fixed subtotal₹3.72
OPEX at Current Utilisation (60%)
Item₹ Cr/yr
Variable (scaled to util%)
Fixed (unchanged)₹3.72
Total OPEX at util%
DPR v16 base (60%, export PS ₹42, no CTAB/stearic)₹11.96 Cr
DPR v15 was (60%, incl CTAB/stearic, domestic ₹26)₹13.38 Cr
OPEX Waterfall — Top 5 Costs
Revenue Breakdown at Current Utilisation
StreamVol (MT/yr)Price₹ Cr/yrShare%
Precipitated Silica
Nano-PCC
Desilicated residue
Total Revenue100%
Revenue at All Utilisation Levels (current prices)
Util%RevenueVar OPEXEBITDAMargin%
Multi-Year P&L with Phase 1B (Month 18) — Current Assumptions
YearUtil%PhaseRevenueVar OPEXFixedEBITDAEBITDA%DSDSCR
Phase 1B (Month 18): adds 4.568 MT/day purchased RHA, from Y1 accruals (₹1.50 Cr capex — not in bank debt). DPR v16: ₹12.43 Cr debt, DS = ₹2.66 Cr/yr post-moratorium vs ₹4.07 Cr in DPR v15. Savings of ₹1.41 Cr/yr on DS alone.
Contribution/MT RHA
Revenue minus variable cost
Break-even PS price
PCC at current price subsidises
Variable cost/MT RHA
No fixed overhead
PCC subsidy to PS
% of VC covered by PCC alone
NaOH cost/MT RHA
Largest single variable cost
Each 1% NaOH recovery
Saving/yr at 100% Phase 1A
Variable Cost Stack — Per MT RHA
Component₹/MT RHA% of VC
NaOH 48% lye
CaO quicklime
Packing + transport
Electricity (variable)
RHA (purchased)
CTAB (if included)
Stearic acid (if included)
Total Variable Cost100%
Break-even PS Price at Different PCC Prices
PCC PriceMin PS (₹/kg)vs StandardStatus
Contribution at Different Price Scenarios
ScenarioPS ₹/kgPCC ₹/kgContrib/MTAnn. (100%)
Floor EBITDA at Different Utilisation Levels — Current Prices
ScenarioRHA MT/dAnnual MTContributionFixed OPEXEBITDADSCR (morat)Net Cash
Add-On Capital Projects — ROI Updates with Current Assumptions
ProjectCapexSaving/yrEBITDA/yrPaybackFund FromPriority
▶ COMMISSION DAY 1 — include in commissioning budget
Draft-tube causticiser
NaOH 82→87% + sealant PCC direct (d50 0.5–0.8µm)
₹0.35 Cr Commission budget P1 NOW
CaO slaking HX (plate heat exchanger)
15.2 GJ/day slaking exotherm → NaOH feed pre-heat
₹0.12 Cr 0.8 yr Commission budget P1 NOW
Spray dryer WHR recuperator
6.5 GJ/day exhaust → inlet air pre-heat
₹0.08 Cr 0.8 yr Commission budget P1 NOW
▶ Y1 MINOR CAPEX — fund from early operating cash
ETP: solar evaporation pond (0.25 acre)
HDPE-lined, 2000 mm/yr Sangareddy evaporation → reduce ZLD duty
₹0.05 Cr ₹0.04 Cr ₹0.04 Cr 1.3 yr Y1 cash P2 Y1
ETP: fish pond (0.5 acre catla/rohu)
ZLD polished water → aquaculture → ₹130/kg at Sangareddy market
₹0.07 Cr ₹0.03 Cr ₹0.03 Cr 2.3 yr Y1 cash P2 Y1
ETP: ZLD salt cake Na₂CO₃ partial recovery
30–40 MT/yr; avoids disposal fee + ₹10,000/MT revenue
₹0.15 Cr ₹0.06 Cr ₹0.06 Cr 2.5 yr Y1 cash P2 Y1
Solar +150 kWp (to DISCOM 400 kWp cap)
80% of 500 kW sanction = 400 kWp max; DPR has 250 kWp; +150 kWp incremental
₹0.45 Cr Y1-Y2 accruals P2 Y2
▶ Y2 ACCRUALS — after Phase 1B revenue established
CO₂ bottling plant (1.5 MT/day industrial)
MEA absorption; stripper heat from THU surplus (4.5 GJ/day, zero cost); 495 MT/yr
₹1.50 Cr Y2 accruals P3 Y2
TOTAL (all add-on projects) ₹2.77 Cr 1.4 yr avg
Y1 Cash Waterfall (Full Optimisation Scenario)
Item₹ Cr
EBITDA (export PS ₹42/kg, no CTAB/stearic, 60% util)
Less: moratorium interest (₹12.43 Cr × 10.5%)
T-IDEA SGST rebate (Y1–Y5)+₹1.26 Cr
Total Y1 deployable cash
Phase 1B capex (non-negotiable first priority)−₹1.50 Cr
Heat integration (commission budget)−₹0.20 Cr
ETP innovations−₹0.27 Cr
Solar +150 kWp (net post-subsidy)−₹0.32 Cr
Remaining for CO₂ plant (Y2)
MVR — Already in DPR (Mandatory)
MetricValue
MVR capex₹1.50 Cr (in DPR)
Evap heat without MVR167.1 GJ/day
Evap heat with MVR58.5 GJ/day (−65%)
Heat saved108.6 GJ/day
Without MVR: thermal deficit−25.6 GJ/day → plant stops
Thermal surplus with MVR (Y1)83 GJ/day
THU typeTherminol 55 / Dowtherm A
THU operating temp180–220°C, atmospheric
MVR is mandatory from Day 1. The ₹1.50 Cr is already in the bank term loan. This is not an "add-on" — it is foundational to plant operation.
EBITDA Sensitivity — Change in Key Assumptions from Current (₹ Cr/yr at current utilisation)
Assumption−30%−20%−10%Base+10%+20%+30%
Positive sensitivities (prices go up = good) shown in green. Negative (cost goes up = bad) shown in red. Base = current assumptions in sidebar.
Scenario Comparison (at 60% utilisation)
ScenarioOPEXRevenueEBITDADSCR (morat)Net Cash Y1
Product Qualification Tracks
GradeQual. TimeRevenue LiveSpecTarget Customers
Bulk PCC — Coatings2–3 monthsDay 1 (Month 2)2 µm d50, brightness ≥97Asian Paints, Berger, Nerolac
Standard PS1–2 monthsDay 1 (Month 1)BET 140–165 m²/gGCC rubber compounders, animal feed
Sealant PCC (stearic coated)4–6 monthsMonth 60.7 µm d50, stearic coatedPidilite, Sika, Henkel
HDS PS (Green Tyre)6–12 monthsMonth 15–18CTAB ≥175 mg/g, CIPD ≥80%Apollo, MRF, Ceat, JK Tyre, BKT
Dental / Food PS (FSSAI E551)18–24 monthsY3 (Month 36)Pb ≤1 ppm, d50 ≤12 µmColgate, HUL, Dabur, export pharma
Revenue Unlock Sequence
MonthMilestoneRev Impact
Month 1–2Std PS + bulk PCC — first commercial sales+₹6–8 Cr/yr base
Month 6Sealant PCC qualification completePCC: ₹10→₹26/kg
Month 10FSSAI E551 application filed (dental PS)18M cycle begins
Month 12Commercial production at full commissioningFull Phase 1A
Month 15–18HDS qualification at Apollo/MRF/CeatPS: ₹26→₹46–50/kg
Month 18Phase 1B installed from Y1 accruals+₹9 Cr/yr
Month 36FSSAI E551 certified + dental revenue livePS: up to ₹92/kg
Implementation Timeline — Key Milestones
Month 0
Financial close · land possession · PMC appointed
Equity infusion · bank drawdown · site mobilisation
Month 1
Customer engagement begins
HDS qualification samples planned · PCC coatings first contact · engineering freeze
Month 2–4
Lab validation
Causticisation recovery trial (target 82%+) · SiO₂ extraction validation · Na-balance · draft-tube causticiser install decision
Month 3–8
Civil + equipment procurement
THU (thermal heating unit with oil) · MVR evaporator · leach reactors · filter presses · spray dryers · ETP+ZLD · CEMS installation
Month 8–10
Equipment installation · mechanical completion
E&I wiring · SCADA commissioning · TSPCB CEMS certification
Month 10
FSSAI central licence application filed
12–18 month cycle; file at commissioning, not later
Month 11
Trial samples to target customers
PS BET/PSD characterisation · PCC particle size / brightness · HDS qualification batch
Month 12
Commercial production begins
Standard PS + bulk PCC · 60% utilisation ramp-up · first invoices
Month 18
Phase 1B from Y1 accruals (₹1.50 Cr)
+4.568 MT/day RHA · +3.996 MT/day PS · +6.160 MT/day PCC · export stream activated
Month 36 (Y3)
FSSAI E551 certified · dental/food revenue live
PS price ₹92–95/kg · Colgate/HUL/Dabur offtake · export pharma enquiries
Site Scorecard — Kothakota (Wanaparthy) vs Alternatives
FactorKothakota / WanaparthyTSIIC SangareddyGeneric TSIIC RuralWeight
Land cost₹30L/acre · 12 ac = ₹3.60 Cr total₹1 Cr/acre · 3 ac = ₹3.00 Cr (confined)₹20–40L/acre★★★★
Expansion room12 acres → Phase 2 + 1 MW solar + ETP ponds3 acres — Phase 2 impossible on-siteDepends on purchase★★★★★
Distance from Hyderabad~130 km · 3–3.5 hr drive~55 km · 1 hr drive80–150 km typical★★★
NaOH tanker accessNH-44 / SH route — check last-mile road qualityNH-65, excellent logisticsVaries★★★★★
CaO proximity (Piduguralla)~190 km (via Nandyal)~170 km (via Miryalaguda)150–200 km typical★★★
Rice husk supplyWanaparthy, Gadwal rice mills nearbyMedak, Nizamabad — 60–80 kmVaries by region★★★★
Water (groundwater)Krishna basin edge — good aquifer. Verify 150+ KLD borewell yieldGroundwater declining; industrial water supply neededSurvey required★★★★★
DISCOM power reliabilityTSSPDCL rural feeder — 6–10 hr cuts possible; DG + solar mitigatesIndustrial feeder, <2 hr cuts/monthRural: 4–8 hr cuts★★★★
Skilled workforceLimited local pool; need housing incentive / transportIndustrial corridor; easy hireThin local pool★★★
TSPCB consent speedDistrict TSPCB office — 4–6 monthsTSIIC industrial zone — 3–4 months3–6 months★★
VerdictSTRONG if checklist passes (see below)Good infra, limited expansionCase by case
Kothakota Go / No-Go Checklist — Verify Before Purchase
#TestMinimum PassHow to verify
1Borewell test2 borewells · 150+ KLD combinedHydrogeology survey ₹30–50K; test borewell before land deal
2Tanker road access26-tonne NaOH tanker can reach site gateDrive a truck physically; check culvert load ratings
3DISCOM 500 kW sanctionTSSPDCL confirms 500 kW HT/LT at site feederWritten feasibility from TSSPDCL Wanaparthy before signing
4Title clear + pattaSingle patta, no encumbrance, no court disputeDharani portal + local advocate search
5Zoning / land useIndustrial/agro-industrial conversion possibleCollector office + DTCP; avoid SRA land
6Flood zoneNot in flood-prone area (Krishna basin check)NDMA flood map + local knowledge of last 10yr floods
7Rice husk within 30 kmAt least 3 rice mills within 30 km, 50+ MT/day capacityDrive and meet mill owners; get informal commitment
If all 7 pass: buy Kothakota. 12 acres at ₹30L/acre = ₹3.60 Cr total. Use saved land money (vs TSIIC ₹3 Cr/3 acres) for Phase 2 foundation and solar. The 9 extra acres are a free option on ₹15+ Cr Phase 2 expansion.
Land Strategy — What to Prioritise
PriorityRationale
1. Expansion room > cheap price12 acres lets you run Phase 2 (₹15+ Cr, 3× revenue) without acquiring adjacent land. In 5 years TSIIC Sangareddy will have no room to expand.
2. Water > everything84 KLD Phase 1A, 110 KLD Phase 1B. A dry borewell can kill the project. Verify first, negotiate price second.
3. Tanker road access > proximity to HydNaOH is hazmat — 3 tankers/week. If the last 5 km are broken track roads you will pay ₹3,000+ per trip extra and risk refusals. More important than distance to Hyd.
4. Closest to Hyd is lowest priority3.5 hr is manageable with the right management structure. Proximity adds ₹2–3 Cr to land cost and limits expansion — poor trade-off. Remote is fine if managed right.
Remote Management Architecture — 95–98% Efficiency from 130 km Away
The Core Principle
A 3.5 hr commute rules out daily supervision. What you need instead is a self-running plant where you manage outcomes, not activities. This requires: (1) strong plant manager as your proxy, (2) process automation so operators monitor alarms — not tune parameters, (3) contractor AMCs so you buy uptime SLAs not headcount, (4) a KPI dashboard you can read on your phone at 7 AM.
Guardrails — Non-Negotiable
#GuardrailHow
1Morning report by 6 AM dailyPlant manager sends WhatsApp report: production MT, NaOH consumed, any downtime, QC pass/fail
2SCADA mobile accessIgnition SCADA perspective app — live pH, temperatures, flow rates on your phone
3Spend authority matrixPlant manager: up to ₹50K self; up to ₹2L WhatsApp approval; above ₹2L formal PO from Hyd office
4CCTV / IP camera4–6 cameras on critical points (chemical storage, reactor area, loading bay, main gate) — live on phone
5Daily batch record in ERPEvery batch: raw material lot, quantities, QC result, dispatch note — no paper-only records
6Fortnightly site visitPromoter visits every 2 weeks (stay 1–2 nights). Monthly full review meeting with all division heads.
7PLC auto-shutoffTemperature, pH, pressure limits trigger alarm + auto-shutoff. No operator discretion on safety parameters.
8NaOH inventory alertMinimum 7-day stock trigger auto-PO to supplier. Never run out — NaOH is the single-point-of-failure input.
Cadence of Oversight
FrequencyWhoWhat
Daily 6 AMPlant Manager → PromoterWhatsApp: production, inputs, issues, QC status
Weekly FridayPlant Manager video call30-min review: weekly output vs target, raw material levels, upcoming orders, any maintenance
FortnightlyPromoter on-sitePhysical inspection, operator interactions, contractor review, bank/customer visits if needed
MonthlyAll division headsP&L review, KPI vs targets, contractor SLA review, next month plan
QuarterlyCSIR-IICT / IIT advisorProcess optimisation review, NaOH recovery audit, product quality benchmarking
Technology Stack for Remote Management
ToolPurposeCost
Ignition SCADA (Inductive Automation)Live process data, alarms, trends on mobile~₹3–5L one-time
IP CCTV (Hikvision/Dahua)Visual monitoring of plant floor~₹1–2L
ERP lite (Zoho Books / Tally Prime)Batch records, purchase orders, invoicing₹20–40K/yr
WhatsApp Business + Google WorkspaceDaily ops communication, shared dashboards₹5–10K/yr
GPS fleet tracking on tankersKnow when NaOH delivery is arriving₹500/vehicle/month
Organisation Architecture — Promoter-Led Hybrid Model
MANAGEMENT DIVISION
Hyderabad HQ (You)
• Raw material procurement
• Customer relationships
• Export & documentation
• Finance, banking, compliance
• Contract management
• IP protection
• Strategic decisions
Headcount: 1 promoter + 1 admin + 1 accounts
PLANT MANAGER
On-site (Critical hire)
• Day-to-day ops oversight
• All 4 divisions report here
• Contractor liaison
• Daily report to promoter
• Emergency authority
• Recruitment + HR on-site
• TSPCB compliance
CTC: ₹18–24L/yr · 15+ yr exp chemical plant
PROCESS DIVISION
Own staff + NDA
• Leaching + precipitation
• Causticisation + PCC
• Spray drying
• Batch record keeping
• 3 shifts × 2 operators
• 1 process chemist (day)
• Strict IP NDAs
Headcount: 7 own staff · Cost: ₹42L/yr
UTILITIES DIVISION
Contracted AMC
• ETP/ZLD: Thermax AMC
• THU: Forbes Marshall AMC
• Solar: Installer AMC
• DG: Kirloskar AMC
• MVR: IPEC AMC
• All on SLA: 98% uptime
• No own hire for utilities
AMC cost: ~₹40L/yr · Zero own headcount
QC / LAB DIVISION
Hybrid model
• 1 own QC technician (on-site)
• Daily BET, PSD, pH testing
• Monthly external: NABL lab
• Quarterly: CSIR-IICT Hyd
• Annual: IIT-H process audit
• COA certification for export
• FSSAI samples management
Cost: ₹8L own + ₹6L external = ₹14L/yr
MAINTENANCE DIVISION
1 resident + AMCs
• 1 resident maintenance tech
• Daily preventive maintenance
• Manages spare parts store
• Escalates to vendor AMC
• Handles electrical issues
• Filter press operation
• Lubrication schedules
Cost: ₹6L own + ₹10L spares/consumables
INSTITUTIONAL EXPERTISE
Advisory layer
• CSIR-IICT: Process troubleshoot
• IIT Hyderabad: Optimization
• NITW: Internship pipeline
• Commissioning consultant: First 6 months only
• PDIL or similar: Startup support
• IP attorney: Patent + NDA drafting
Cost: ₹8–12L/yr advisory retainers
IP PROTECTION
Non-negotiable layer
• All operators: signed NDA
• Process recipe in SCADA only (no paper)
• Operators see alarms, not ratios
• Key process params: promoter + PM only
• CTAB/surface treatment: locked cabinet
• HDS recipe: separate access level
• Export price list: confidential
Cost: ₹2–3L/yr (legal + SCADA access mgmt)
Total Cost of Proposed Structure (₹ Cr/yr)
DivisionOwn Staff CostContractor / AMCTotal
Management (Hyd HQ)₹12L₹12L
Plant Manager₹22L₹22L
Process Division (7 staff)₹42L₹42L
Utilities (AMC only)₹0₹40L₹40L
QC / Lab₹8L₹6L₹14L
Maintenance (1 own + spares)₹6L₹10L₹16L
Institutional (CSIR-IICT, IIT-H)₹10L₹10L
IP / Legal₹3L₹3L
Total₹90L₹69L₹1.59 Cr/yr
DPR v16 budgeted labour₹1.20 Cr/yr (25 staff)₹1.20 Cr base
Delta (restructured vs DPR)+₹0.39 Cr/yr
The +₹0.39 Cr incremental cost buys: (1) 98%+ equipment uptime via AMCs, (2) zero specialist hiring (ETP engineer, boiler engineer, etc.), (3) institutional process knowledge you can't build in 2 years, (4) legal IP protection. At ₹15 Cr+ annual revenue, this is a 2.6% overhead — not a cost, an insurance policy.
Commissioning Strategy — First 6 Months (Critical for New Promoter)
MonthActionWho
M −3 to M0Hire plant manager before equipment arrives — they oversee installationPromoter recruits via Naukri/HeadHunters India
M0–M6Commissioning consultant on-site full time (PDIL/private ChemE)Contract: ₹3–5L/month for 6 months
M1–M3CSIR-IICT NaOH recovery lab trial at pilot scale before full commissioningCSIR-IICT MOU, samples from first run
M6Commissioning consultant exits; CSIR-IICT moves to quarterly advisoryPlant Manager now fully independent
M6–M12Operate at 60% intentionally — learn before pushing throughputAll divisions; weekly ops review
M12+Ramp to 75–90% with institutional confidence. Push NaOH recovery to 85%+Process Division + IIT-H optimization
Operations Model — Shift Structure & Automation
24×7 is Non-Negotiable for This Process
Wet chemistry with continuous NaOH circuit, MVR evaporator, and spray dryers cannot safely start/stop daily. A 16-hr or 12-hr shift model would: (1) waste 8–12 GJ/day bringing THU to temperature, (2) risk crystallisation and scaling in evaporator circuits on cool-down, (3) reduce effective capacity to 55–67% of design. The economics of Phase 1A require 330 days × 24 hrs — full stop.
Minimum Staffing Per 8-Hour Shift
RolePer ShiftShift typeNotes
Chemical process operator2All 3 shiftsMonitors PLC alarms, manages filter press loading
Helper / packer1All 3 shiftsBagging, labelling, stacking — manual
Shift supervisor1Day + EveningNight shift: senior operator acts as supervisor
Process chemist (QC)1Day shift onlySampling, COA, daily batch testing
Plant manager1Day shift onlyOn-call 24×7 for emergencies
Maintenance technician1Day shift onlyOn-call for night breakdown via AMC escalation
Total own headcount13 persons (9 shift operators/helpers + 4 day-shift specialists)
Automation Level by Process Step
Process StepAutomation%What remains manual
RHA weighing + feed80%Bag slitting, conveyor jam clearing
NaOH dilution + dosing90%Tank top-up verification
Leach reactors (temp, pH, time)85%Visual check, sample grab
CO₂ precipitation (pH-stat)95%Sample for BET verification
Filter press (PS)50%Loading cloth, opening, cake discharge — unavoidably manual
Causticisation (draft-tube)90%CaO bin refill (3×/day)
CaO slaking85%Quicklime unloading from truck
MVR evaporator95%Scale inspection monthly
Spray dryer90%Nozzle inspection, bag change
ETP / ZLD95%Salt cake removal (weekly)
Bagging + labelling20%Almost entirely manual — highest labour intensity point
Overall plant~80%Filter press + bagging are the manual bottlenecks
80% automation means 2 operators per shift can monitor a 15 MT/day plant. The PLC handles temperature, pH, flow, timing. Operators respond to alarms and handle the physical steps that chemistry cannot automate.
O&M Cost Model & Critical Spares Inventory
AMC Structure — Buy Uptime, Not Headcount
SystemContractorAMC ₹/yrSLA guarantee
ETP + ZLD (25 KLD)Thermax Enviro / Enviro Labs Hyd₹10–14L98% uptime, 24hr response, quarterly service
THU + thermal circuitForbes Marshall (Pune)₹6–9LAnnual strip-down, oil analysis, safety cert renewal
Spray dryers (×2)Raj Process Equipments (Pune)₹5–8LNozzle, atomizer, bag filter replacement; 48hr callout
MVR evaporatorIPEC Pune / original vendor₹4–6LCompressor bearing, seals; scale cleaning protocol
Filter presses (×2)Star Filter Press / local₹2–4LCloth replacement, plate inspection semi-annual
Solar PV (250 kWp)Installer AMC₹2–3LCleaning, inverter check, performance guarantee
DG set (200 kVA)Kirloskar service₹2–3LRunning hours-based service, load bank test quarterly
SCADA + instrumentationSystems integrator₹2–3LPLC firmware, sensor calibration, alarm management
Total AMC₹33–50L/yrAvg ₹42L — already in OPEX model
Critical Spares — 90-Day Buffer (₹30–35L one-time stock)
ItemQtyWhy critical
Filter press cloth sets (full replacement)2 sets₹8LWears every 60–90 days; no plant without it
Centrifugal pump impellers + seals5 sets₹5LNaOH corrodes; 6-month replacement cycle
MVR compressor seals + bearings1 set₹5L12–18 month life; long lead-time item
pH electrodes (glass, combination)12₹2LConsumable; 2–3 month life in NaOH service
THU Therminol 55 oil (top-up)200 L₹4LAnnual top-up; degrade under air ingress
Spray dryer nozzles + atomizer tips6₹3LHigh wear; affects particle size consistency
PLC I/O cards (S7-1200 modules)2₹3LFailure = plant stop; 2-week import lead time
Pressure relief valves (set-point tested)3₹3LSafety-critical; must be tested annually
NaOH tank HDPE liner repair kit1₹2LWeld repair kit for HDPE/PP-lined vessels
Total 90-day spares₹35LOne-time investment; kept on shelf at plant
Rule: Never let spares drop below 30-day minimum for consumables (pH electrodes, filter cloths, nozzles). Plant manager's standing order: reorder trigger at 50% of buffer stock. A single filter press cloth failure with no spare = 8–12 hr plant stoppage = ₹2–3L lost production.
Workforce Plan — Captive + Contract Model
Full Headcount at Steady State (Phase 1A, 24×7)
RoleTypeCountCTC ₹L/yrLives on-site?
▶ OWN PAYROLL — IP-sensitive, permanent
Plant ManagerOwn122Yes — 2BHK on-site
Process chemist / QCOwn18Yes — 1BHK (Mon–Fri)
Shift operators (chemical)Own64–5 each2 on-site · 4 local commute
Maintenance technicianOwn15On-site · 1BHK
Admin / accountsOwn14Wanaparthy town commute
Security guardsOwn23 eachRotating · quarters on-site
▶ LABOUR CONTRACT — via registered contractor
Helpers / packers (3 shifts)Contract92.5–3 eachLocal village pool; transport allowance
Cleaning / housekeepingContract22 eachLocal
Driver (for tanker + product)Contract13Local
▶ AMC / THIRD-PARTY (no headcount, billed as OPEX)
ETP/ZLD operator (Thermax)AMCVisits per contract schedule
THU service (Forbes Marshall)AMCQuarterly + on-call
Total own payroll headcount12~₹70L/yr5 captive on-site · 7 commute
Contract workers (via contractor)12~₹36L/yrLocal daily
Captive Accommodation Plan (on 12-acre site)
UnitSpecCountCapex ₹L
Plant Manager residence2BHK · 850 sqft · RCC · semi-furnished112
Technical staff quarters1BHK · 450 sqft each · block design4 units20
Security cabin + quartersMain gate cabin + 2 sleeping rooms13
Canteen / messBasic kitchen + dining for 30 people; contractor-run14
Visitor / promoter room2-room guesthouse for fortnightly visits15
Total accommodation capex₹44L
Accommodation is a retention tool, not a luxury. A plant manager who lives on-site responds to a 2 AM alarm in 5 minutes. A plant manager who commutes 40 km avoids night calls. For ₹44L you buy 24×7 operational coverage and dramatically reduce turnover risk for your two most critical roles. Build it before commissioning.
Canteen / Mess — Contract It Out
Give canteen contract to a local caterer (Wanaparthy town). Cost: ₹80–120/meal × 3 meals × 30 people = ₹8–11L/yr. Deduct ₹30/meal from staff salary; net cost to company ₹3–5L/yr. Eliminates food management entirely — zero your time on this.
Plant Layout — 12 Acres, Kothakota (Phase 1A + Phase 2 Reserved)
PROCESS BUILDING
3,500 sqft · RCC frame
Leach reactors ×3
Precipitation tanks ×2
Draft-tube causticiser
CaO slaker
Filter presses ×2
~0.5 acres footprint
SPRAY DRYER + MVR BLOCK
2,000 sqft · separate
Spray dryers ×2
MVR evaporator
Feed pumps
Bag filter / cyclone
Bagging station
~0.3 acres footprint
THU + FURNACE BLOCK
1,200 sqft · fire-rated RCC
Furnace (20 TPD rice husk)
THU oil heater
Flue gas cleaning
CO₂ roots blower
Ash collection + RHA store
~0.2 acres · fire setback
PRODUCT WAREHOUSE
6,000 sqft · PEB shed
PS bagged stock (25 kg)
PCC bagged stock
CO₂ cylinders (future)
QC hold area
Dispatch bay (2 trucks)
~0.6 acres footprint
RAW MATERIAL STORE
RHA silo / shed: 300 MT
CaO covered shed: 200 MT
NaOH HDPE tank farm: 3×50KL
CTAB/stearic drum store
Hazmat bund + HDPE lining
~0.4 acres · bunded
ETP / ZLD BLOCK
ZLD plant (25 KLD)
Effluent holding tank
Solar evap pond (0.25 ac)
Fish pond (0.5 ac, future)
ZLD salt cake store
TSPCB monitoring point
~1.0 acre total
UTILITIES + ADMIN
HT/LT panel room
DG set (200 kVA)
Solar inverter room
SCADA / control room
Admin + accounts office
QC lab (BET/PSD/XRF)
~0.2 acres footprint
PHASE 2 RESERVED
~5 acres held vacant
Phase 2 production line
1 MW solar farm
CO₂ bottling plant
Silica gel side line
Staff expansion
~5 acres — do not build yet
Phase 1A built-up footprint: ~3 acres + 1 acre ETP + 1 acre roads/drainage/accommodation = ~3 acres active, 9 acres future. 1300 ft road frontage = ~3 truck bays + separate tanker entry + emergency exit simultaneously.
Plant Setup — Stage-by-Stage Roadmap (Month 0 = Financial Close)
M −6 to M0
Pre-close
Site acquisition + due diligence + company setup
Borewell test · Title search + Dharani · DISCOM 500 kW feasibility letter · Land registered · TSPCB CTE application filed · SPICe+ company incorporation · DPIIT recognition · Bank DPR submission · IEC registration · Hire plant manager (starts M−1)
M0–M1
Mobilise
Financial close + site handover + PMC appointed
Equity infusion + bank drawdown · PMC / project manager appointed · Site fencing + security + temporary power + site office cabin · Soil test + topographic survey · Groundwork for boundary wall · Commissioning consultant engaged (PDIL or private ChemE) · Long lead-time equipment purchase orders placed: spray dryers, MVR, furnace+THU
M1–M3
Civil
Civil construction — all buildings simultaneously
Process building (RCC frame, 3,500 sqft) · Spray dryer + MVR block · THU furnace room (fire-rated RCC, isolated) · Product warehouse (PEB shed) · Raw material storage (bunded, HDPE-lined) · ETP/ZLD civil · Accommodation block (5 units, PM house, canteen) · Internal roads, drainage, hardstanding · DISCOM HT connection civil work · Borewells (2) + OHT + underground sump · Solar panel civil (foundations)
M3–M6
Procurement
Equipment delivery + erection begins (parallel with civil)
Medium lead equipment arrives: leach reactors, filter presses, causticiser, tanks, pumps · Process piping (HDPE/CPVC) prefabrication · Electrical cable tray + conduit laying · Instruments arrive (pH sensors, temperature, flow meters) · PLC panels (S7-1200) factory acceptance tested · Long lead equipment expected: spray dryers arrive M4, MVR M5 · NaOH HDPE tank farm installation · CaO covered shed completed
M5–M8
Erection
Equipment installation + mechanical completion
All process equipment set on foundations · Process piping welded and hydro-tested · Electrical cabling complete · PLC panel installed + wired · Instrument loop checks · THU oil (Therminol 55) filled and heated for first time · Spray dryer trial run (water only) · MVR commissioning · Solar array installation + DISCOM interconnection · DG set load tested · ETP/ZLD commissioning · CEMS installed on furnace stack · ZLD system water trial
M8–M10
Pre-comm
Pre-commissioning trials + regulatory clearances
TSPCB CEMS certification (mandatory before commercial ops) · CTE → CTO (Consent to Operate) application submitted · Fire NOC from District Fire Officer · Factory License application · Water trial: NaOH circuit (run water, check all leaks) · Chemical trial: dilute NaOH leach (no RHA — just prove circuit integrity) · pH calibration across all instruments · SCADA go-live: all sensors visible on HMI and mobile · FSSAI central licence application filed (start 12–18 month clock) · Customer engagement: first lab samples from trial batches sent to 3 SE Asia brokers and 2 Indian rubber compounders
M10–M12
Commissioning
Commercial commissioning — first real production batches
First rice husk combustion run · First RHA leach batch (measure extraction efficiency, record Na balance) · First PS precipitation batch (measure BET, PSD — should hit 140–165 m²/g standard grade) · First causticisation batch (measure NaOH recovery %, expect 78–82% initially) · First PCC characterisation (d50, brightness) · First spray dryer product (check moisture, particle size) · All results to CSIR-IICT for validation · Adjust process parameters with commissioning consultant · First commercial batch by end M12
M12–M18
Ramp-up
Commercial production ramp — 60% → 75% → stabilise
Month 12: First invoices, first export FCL to SE Asia broker (standard PS, ₹42/kg FOB) · Month 13–15: Optimise NaOH recovery (target: 82% → 85%) · Month 15: HDS qualification samples to Apollo/MRF/Ceat (start 3–6 month approval clock) · Month 16: TSPCB first annual inspection · Month 18: Phase 1B equipment installed from Y1 accruals (₹1.50 Cr) · Month 18: Load enhancement application to DISCOM (if solar expansion needed) · Month 18: First sealant PCC qualification samples to Pidilite/Sika
M18–M36
Optimise
Stabilisation + grade upgrade + export scale-up
NaOH recovery pushed to 86–88% (draft-tube optimisation with CSIR-IICT) · HDS qualification approved: Apollo/MRF offtake begins (PS: ₹45–47/kg) · Phase 1B running at 75%: total RHA 19.6 MT/day · Sealant PCC to Pidilite/Sika pipeline · FSSAI E551 certification expected ~Month 28–30 · CO₂ bottling plant feasibility study (from Y2 accruals) · Phase 2 detailed engineering begins (self-funded) · Promoter fully in commercial mode: customer contracts, export, R&D direction
Promoter Role — What You Own vs What You Delegate
What You Must Own — Cannot Delegate
DomainWhy you, not a professional
Customer relationships & ToA negotiationInstitutional buyers (Apollo, Pidilite, Asian Paints) sign with promoters, not plant managers. Your credibility and equity are the collateral.
Export — IEC, LC management, broker relationshipsLC discounting and export credit are in your name. The bank relationship is yours.
Capital allocation decisionsPhase 1B timing, Phase 2 GO/NO-GO, which grade to invest in qualifying first — all strategic, yours.
IP protectionYou own the process IP. NDAs are signed with you as counterparty. Patent filing (if any) = your name.
Banking & compliance signing authorityBank covenants, ROC filings, TSPCB annual returns — director signature. Cannot delegate legally.
R&D directionWhich grade to pursue next, which customer spec to chase, when to file FSSAI — strategic calls that set the revenue curve for the next 3 years.
What You Delegate — Never Touch Operationally
DomainWho owns itYour oversight tool
Day-to-day plant operationsPlant Manager6 AM daily report + SCADA phone
Process parameter tuningPM + commissioning consultantMonthly batch record review
Equipment maintenanceMaintenance tech + AMCMonthly uptime % KPI
ETP/ZLD complianceThermax AMC + Plant ManagerTSPCB inspection report
QC testing and COAQC tech + NABL external labWeekly COA summary
Labour managementPlant ManagerHeadcount + attendance in ERP
Raw material local logisticsPM + procurement adminInventory levels on dashboard
TSPCB day-to-day submissionsPlant Manager + consultantAnnual summary review
You do NOT need to know: how to operate a spray dryer, NaOH titration procedures, PLC programming, TSPCB form numbers.
You DO need to understand: BET/CTAB (what they mean for price, not how to measure), NaOH recovery% (what it does to OPEX), utilisation% (what it does to EBITDA), export spec requirements (what buyers need, not how to test). The knowledge gap in wet chemistry is not a blocker — it is exactly what the plant manager + CSIR-IICT are hired to fill.
SLA Enforcement — How to Make Professionals Accountable
Plant Manager KPIs (Performance-Linked Bonus)
KPITargetWeight
Utilisation % vs plan≥ plan ±5%30%
NaOH recovery %≥82% Y1, ≥85% Y225%
Plant uptime (excl planned)≥96%20%
TSPCB compliance (zero notices)Zero violations15%
Daily reports filed on time≥95% of days10%
Annual bonus: 15% of CTC if all KPIs met. 0% if critical KPI (uptime or compliance) missed. Paid quarterly to maintain motivation.
AMC Contractor SLAs (Liquidated Damages)
SystemUptime SLALD clause
ETP / ZLD98%₹5,000/hr downtime beyond 48hr
THU system99%₹8,000/hr production loss
Spray dryers97%₹5,000/hr per unit
MVR evaporator98%₹8,000/hr (plant stopper)
LD clause language: "Contractor shall pay ₹X for each hour of unplanned downtime exceeding 8 hr in any calendar month, capped at 10% of annual AMC value." Have contract reviewed by industrial lawyer before signing.
Institutional Partner Accountability
PartnerDeliverableTrigger payment
CSIR-IICTNaOH recovery improvement roadmapPer milestone, not retainer
Commissioning consultantCommissioning sign-off report30% mobilisation, 70% on CTO
IIT-H advisoryProcess optimisation report (quarterly)Quarterly deliverable-based
NABL labCOA with accreditation stampPer test batch
Key principle: never pay retainers without deliverables. Every payment must trigger a document, report, or measurable outcome.
TPC (DPR v16)
₹19.13 Cr
Pending vendor RFQs ±10%
Target debt
₹12.43 Cr
65% of TPC, 7-yr tenure
CGSS cover (80%)
₹9.94 Cr
Guaranteed by NCGTC
Uncovered (20%)
₹2.49 Cr
Land (₹7 Cr) covers 2.8×
Personal exposure
Minimal
Land pledge replaces personal guarantee
Target moratorium
18 months
SIDBI SMILE allows up to 36M
Optimal Financing Stack — Recommended Tranche Structure
TrancheSourceAmountRateMoratoriumGuaranteePriority
A — Core term loanSIDBI SMILE + CGSS guarantee₹8–9 Cr9–9.5%18 months (stated policy)CGSS 80% = NCGTC covers ₹6.4–7.2 CrFILE FIRST
B — Green assets trancheSIDBI 4E / IREDA biomass₹2–3 Cr7.5–8.5%12–18 monthsAsset (THU, solar, ETP, MVR)FILE PARALLEL
C — TDB technology loanTechnology Development Board (DST)₹2–3 Cr5%24 monthsProcess IP + CSIR-IICT letterFILE PARALLEL
D — Working capital CCSame bank as Tranche A₹3 Cr9.5–10%None (revolving)Stock + book debtsAT COMMISSIONING
E — Export packing creditSame bank (IES subvention)₹1–2 Cr5–7%None (per order)LC / confirmed export orderMONTH 12+
If A+B+C all sanctionedBlended rate₹12–15 Cr~7.5–8.2%18–24 monthsMinimal personal exposure
DPR v16 base (SIDBI alone)₹12.43 Cr10.5%12 monthsCGSS only
TDB at 5% on ₹2–3 Cr saves ₹0.11–0.16 Cr/yr in interest vs 10.5%. Over 7 years = ₹0.77–1.12 Cr saved. Worth the 6–9 month application delay if you start now. File with CSIR-IICT collaboration letter as the anchor document.
Scheme-by-Scheme Guide — Active as of 2026
SchemeWhoRateMaxKey conditionStatus
▶ GUARANTEE SCHEMES — reduce bank risk, unlock better terms
CGSS (Credit Guarantee Scheme for Startups)NCGTC / DPIIT0.5% fee/yr₹10 CrDPIIT recognition ✓ already doneACTIVE
CGTMSE 2.0 (Micro & Small)CGTMSE0.75–1.25%₹5 CrUdyam MSME registrationACTIVE
▶ SIDBI SCHEMES — primary lender for this project
SIDBI SMILE (Make in India Enterprises)SIDBI9–9.5%₹25 CrManufacturing, MSME; moratorium up to 36MACTIVE
SIDBI 4E (Energy Efficiency / Environment)SIDBI7.5–8.5%₹10 CrGreen assets: solar, ETP, biomass energyACTIVE
SIDBI SPEED+ (Startup)SIDBI9%₹10 CrDPIIT recognition; fast-track 30-day decisionACTIVE
▶ SPECIALISED LENDERS
TDB Loan (Technology Development Board)DST, Govt India5%50% of project costTechnology development + CSIR/IIT partner; slow (6–9M)ACTIVE
IREDA BiomassIREDA8.5–9%₹3–5 CrBiomass combustion + energy efficiency componentsACTIVE
NABARD Agro-ProcessingNABARD RIDF8–9%₹30 CrAgricultural waste valorization; rural location ✓ACTIVE
▶ WORKING CAPITAL & EXPORT FINANCE
Interest Equalisation Scheme (IES)RBI / all banks−2 to −3%No limitPre+post shipment export credit; 2-3% below normalACTIVE
ECGC Export Credit InsuranceECGC0.5–1% premium90% coverInsures against SE Asia buyer default; essential for new exportersACTIVE
EXIM Bank MSME Export CreditEXIM Bank8–9%₹5 CrFirst-time exporters; market entry supportACTIVE
▶ INCENTIVES & SUBSIDIES (cash-back / tax)
80-IAC Tax HolidayIncome Tax Act100% exemption3 yrs of 10DPIIT recognition ✓; file after first ITRACTIVE
RoDTEP (Remission of duties on exports)DGFT0.5–1.5%of FOBAll exported products; claim per shipmentACTIVE
MeitY ECMS (Electronics Component Mfg)MeitY25% subsidy₹50LSCADA, PLC, instrumentation BOM eligibleVERIFY
SISFS (Seed Fund for Startups)DPIITCurrently closed / pausedCLOSED
18-Month Moratorium — Negotiation Script
Standard bank moratorium is 12 months. 18 months requires justification. Here is the documented argument:
ArgumentEvidence
Construction period = 12 monthsCivil + equipment + E&I = 12 months (PMC schedule)
Commissioning stabilization = 6 monthsWet chemistry plants need 3–6M to achieve stable recovery %. First revenue Month 12. Stable revenue Month 18.
SIDBI SMILE allows 36MScheme document explicitly allows up to 36-month moratorium for complex manufacturing
CGSS-backed = bank risk is minimalBank holds NCGTC guarantee — 80% risk transferred. They can afford to be flexible on moratorium.
Interest-during-moratorium offeredPropose: pay interest monthly during moratorium (bank still earns ₹9–9.5%). Only defer principal.
Export revenue from Month 12Provide customer pipeline evidence: SE Asia broker MOU, sample orders
Fallback position: If bank insists on 12M moratorium, negotiate a "step-up repayment" — 50% of EMI in Y2, 100% from Y3. Same economic effect as 18M moratorium on cash flow, but framed differently for the bank.
Carbon / BCR Credits — Register Before Commissioning
Credit typeMechanismPotential ₹/yrRegister timing
PCC carbon fixationCO₂ permanently mineralised as CaCO₃ · 3,089 MT/yr fixed₹38–65L/yrBEFORE commissioning (baseline docs required)
Rice husk biochar / RHAPuro.earth CORC methodology · biogenic carbon in ash₹15–30L/yrBefore commissioning
JCREDITS (Japan BCM)Japan bilateral credit · JETRO facilitates₹20–40L/yrApply via JETRO India post-commissioning
Domestic BIS carbon creditIndia Carbon Market (ICM) · BIS scheme 2026₹10–25L/yrWatch for launch; register early
Total BCR upside (Year 2+)₹83–160L/yrNot in base EBITDA — pure upside
Action before Month 0: Contact Puro.earth (puro.earth) and file baseline documentation for PCC carbon fixation methodology. This is a time-sensitive step — you cannot claim credits retroactively if you didn't document the baseline. One email to Puro.earth's project team costs nothing and could unlock ₹50+ Cr over 10 years.
Personal Exposure Map — How to Stay Protected
ItemExposure typeMitigationResidual personal risk
Term loan ₹12.43 Cr (CGSS-backed)Director guarantee (standard)CGSS covers 80% = ₹9.94 Cr covered by NCGTC. Land pledge (₹3.60 Cr, project site) covers uncovered 20% = ₹2.49 Cr.Minimal — land only, not personal assets
Additional land collateral pledgeProperty mortgagePledge project land first (₹3.60 Cr). Use additional family land (balance up to ₹7 Cr) only if bank insists beyond CGSS cover.Land, not liquid assets
WC facility ₹3 CrHypothecation of stock + debtorsAsset-backed (stock = self-liquidating if business stops). Personal guarantee: negotiate to limit to 1× WC limit only.₹3 Cr hypothecation; minimal cash call risk
Export packing creditLC / export order backedSecured by confirmed LC from buyer — bank has first claim on export receivable.Nil if LC from reputable bank
TDB loan (if sanctioned)Technology IP + process documentationTDB's security is typically process IP + company assets. Personal guarantee negotiable for DPIIT startups.Minimal — IP is the collateral
Key principle: With CGSS backing, the bank's credit exposure is only 20% of the loan (₹2.49 Cr). On ₹7 Cr of land collateral, you have 2.8× over-collateralisation on that 20%. This means you can negotiate: (1) no personal guarantee on the term loan, (2) limit personal guarantee on WC to 1× WC limit only, (3) remove any cross-collateralisation clause. A good CA / project finance lawyer makes this argument during sanction.
Application Sequencing — What to File and When
StepActionTimelineDependency
1Udyam MSME registration (udyamregistration.gov.in)Now — 30 minutesNone — just PAN + Aadhaar
2Contact Puro.earth — baseline documentation for PCC CO₂ fixationThis weekNone — just send project description email
3CSIR-IICT MOU signing — needed for TDB and institutional credibilityMonth −3Company incorporated (CIN done ✓)
4SIDBI application (SMILE + 4E) + CGSS guarantee applicationMonth −3 to −2DPR v16, CMA data, Udyam, DPIIT cert, land docs
5TDB loan application (dbt.gov.in/tdb)Month −3 to −2CSIR-IICT MOU, DPIIT cert, DPR, incorporation
680-IAC tax exemption application (startupindia.gov.in)After first ITR (Y1 end)DPIIT cert ✓; file with first ITR
7ECGC export credit insurance registrationMonth 10 (before first export)IEC registration ✓
8Interest Equalisation Scheme — activate at bankMonth 12 (first export order)Export order / LC in hand
9RoDTEP — register on DGFT portalMonth 12IEC + first shipping bill
10JCREDITS application via JETRO IndiaMonth 18 (post-commissioning)6 months production data