Project Brain — Living Decision Register & PM Dashboard
All cells are editable. Changes exist in this browser session — save to file (Ctrl+S) to preserve.
Company Identity
CompanyFluxara Advanced Renewables & Applications Pvt Ltd
CINU35106TS2026PTC210706
DPIIT246192 — Deep-tech Startup recognised
Promoter viaM/S Surya Industries
ProductPrecipitated Silica (PS) + Nano-PCC Circular Biorefinery
LocationKothakota, Wanaparthy, Telangana (site under acquisition)
DPR versionv17 — 20 TPD PS + 30 TPD PCC · Sept 2026
StatusPre-financial close · Site acquisition in progress
Financials (DPR v17 Locked)
TPC₹21 Cr (±10% pending RFQs)
Debt₹13.65 Cr (65%) @ 10.5%
Equity₹6.70 Cr (35%)
Annual DS (Y2+)₹2.93 Cr/yr (7-yr tenure)
Moratorium target18 months
Y1 EBITDA (export)₹6.2 Cr (positive — no bridge needed)
Y1 DSCR4.3× (above 1.25× covenant)
Break-even utilisation~33% at export prices
Site (Kothakota)
Area12 acres @ ₹30L/acre = ₹3.60 Cr total
Road frontage1,300 ft — 3 truck bays simultaneously ✓
NH access2.5 km from NH-44 ✓
WaterPaddy growing belt — high water table ✓
DISCOMTSSPDCL 500 kW feasibility letter PENDING
Commute from Hyd~130 km · 3–3.5 hr one way → fortnightly visit model
Expansion~9 acres reserved for Phase 2 + 1 MW solar
Accommodation₹44L captive (PM house + 4 staff quarters + canteen)
Promoter Role (Stabilised Operations)
YOURSCustomer relationships · institutional ToA negotiation · exports & LC management · R&D direction · capital allocation · all regulatory signing authority
DELEGATEDay-to-day ops → Plant Manager · Equipment maintenance → AMC · ETP/ZLD → Thermax AMC · QC/testing → QC tech + NABL lab · TSPCB submissions → PM · Labour → contract firm
ADVISORYCSIR-IICT (process optimisation quarterly) · IIT Hyderabad (process research) · NITW (internship pipeline) · Commissioning consultant (Month 0–6 only)
Phase Timeline Overview
Hover over phase bar for details
Pre-close
Mobilise
Civil
Procurement
Erection
Pre-comm
Commission
Ramp-up
Optimise
Key dates: Month 0: Financial close (target Q1 2027) Month 10: FSSAI application filed Month 12: First invoice Month 18: HDS qualification target Month 30: FSSAI E551 certified (dental)
This log captures every major decision made on this project with rationale. Decisions are permanent — add new rows below. Never delete prior decisions.
DateDecisionRationaleAlternatives rejectedStatus
Sep 2026Product: Precipitated Silica + Nano-PCC (not battery carbon)Better domestic + export market. No IP barriers. PCC is obligatory co-product of NaOH recovery — makes both simultaneously. Battery carbon had no viable domestic buyer pipeline.Battery hard carbon (rejected: high capex, no domestic market, import competition from Japan)LOCKED
Sep 2026v17: Hybrid RHA model at 20 TPD PS — 19.4 MT purchased + 3.6 MT bonus RHA = 23 MT/day23 MT/day total RHA from Day 1. 19.4 MT purchased + 3.6 MT free from combustion → 20 MT/day PS + 30 MT/day PCC. Phase 1B concept eliminated — full capacity from Day 1.v16 13 TPD PS with Phase 1B at M18 (rejected: only ₹2 Cr more capex at v17 = ₹25+ Cr/yr more EBITDA; no reason to stage)LOCKED
Sep 2026MVR evaporator mandatory from Day 1Without MVR: 25.6 GJ/day thermal deficit — plant literally cannot run at design throughput. MVR reduces evaporation heat 65% (167 → 58.5 GJ/day). ₹1.50 Cr in bank debt, already included.Deferred MVR installation (rejected: plant cannot operate without it)LOCKED
Sep 2026THU (Thermal Heating Unit with oil) replaces IBR steam boilerTHU uses Therminol 55 oil at 180–220°C, atmospheric pressure. Saves ₹105–120L capex + eliminates IBR registration (8–10 weeks off critical path) + no boiler attendant licence needed. Same 199.3 GJ/day useful heat delivered.IBR steam boiler (rejected: higher cost, IBR registration creates 8–10 week delay, licensed boiler attendant needed)LOCKED
Sep 2026TPC revised to ₹21 Cr (v17 — 20 TPD PS from Day 1)v17 increases capacity to 20 TPD PS + 30 TPD PCC. ₹21 Cr TPC vs v16's ₹19.13 Cr — only ₹2 Cr more capex for ₹25+ Cr/yr additional EBITDA at steady state. Debt ₹13.65 Cr, DS ₹2.93 Cr/yr. DISCOM 750 kW application required (vs v16's 500 kW).v16 ₹19.13 Cr at 13 TPD PS (rejected: leaves 53% of thermal capacity idle and ₹25 Cr EBITDA/yr unrealised)RFQ PENDING ±10%
Sep 2026Export pricing from Year 1 — PS at ₹42/kg FOB (not ₹26 domestic)SE Asia rubber compounders buy standard PS as commodity. No qualification barrier beyond COA + 1 trial batch. ₹42 vs ₹26 = +₹5.42 Cr EBITDA at 60% util. Y1 Net Cash flips from −₹1.55 Cr to +₹4.77 Cr at v17 scale. IEC registration is 2-day process.Domestic-only Y1 (rejected: creates unnecessary cash loss when export is straightforward and higher-value)LOCKED
Sep 2026Kothakota 12 acres at ₹30L/acre as site (pending DISCOM letter)1300 ft road frontage + 2.5 km NH-44 + paddy belt water solves 3 of 7 checklist items immediately. 12 acres at ₹3.60 Cr provides Phase 2 + 1 MW solar + ETP ponds vs 3 acres TSIIC at ₹3 Cr with zero expansion room.TSIIC Sangareddy 3 acres ₹3 Cr (rejected: no expansion room); other TSIIC parks (rejected: higher cost, less land)DISCOM LETTER PENDING
Sep 2026Captive accommodation ₹44L on-sitePlant manager living on-site responds to 2 AM alarm in 5 min vs 40 km commute. Critical hire retention at remote location. PM + QC tech (Mon-Fri) + 2 operators + maintenance tech = 5 people on-site 24×7 coverage.No accommodation (rejected: unacceptable risk for 24×7 chemical plant at 130 km from promoter)INCLUDE IN CIVIL SCOPE
Sep 2026Contractor AMC model for utilities — buy uptime SLAs, not headcountETP/ZLD to Thermax AMC. THU to Forbes Marshall. Spray dryers to Raj Process. MVR to IPEC. ~₹40L/yr total AMC cost replaces hiring 3–4 specialist engineers. LD clauses (₹5,000–8,000/hr) enforce performance.Own utility engineers (rejected: hard to retain specialists in remote location; 3× higher cost for equivalent coverage)LOCKED
Sep 2026Draft-tube causticiser — upgrade from standard to Dorr-Oliver designIncremental cost ₹20–35L. NaOH recovery improves 82% → 86–88% = ₹0.94–1.88 Cr/yr additional EBITDA. Also produces sealant-grade PCC directly (d50 0.5–0.8 µm, ₹26/kg) vs bulk PCC (₹10/kg). Payback <2 months.Standard causticiser (rejected: leaves ₹0.94+ Cr/yr on table for ₹35L incremental cost)ADD TO EQUIPMENT LIST
Sep 2026Phase 1B concept eliminated at v17 — full 20 TPD PS from Day 1v17 starts at full capacity. Phase 1B was the v16 M18 capacity bump (13→17 TPD PS); at v17 20 TPD from commissioning, Phase 1B is redundant. Y1 Net Cash = +₹4.77 Cr. Phase 2 (second production line) to be self-funded from Y2+ accruals.Phase 1B at M18 (rejected: v17 delivers same output from Day 1 without needing a staged expansion)LOCKED
Sep 2026SIDBI SMILE + CGSS as primary financingSIDBI allows 18–36 month moratorium. CGSS covers 80% of loan (NCGTC guarantee) = only ₹2.49 Cr uncovered. Land collateral (₹3.60 Cr project site) covers uncovered portion 1.44×. Minimal personal exposure. Target 9–9.5%.Commercial bank alone (rejected: higher rate 10.5%, 12-month moratorium only, full personal guarantee required)APPLICATION IN PROGRESS
Sep 2026TDB loan in parallel — ₹2–3 Cr at 5%TDB's 5% rate saves ₹0.11–0.16 Cr/yr vs 10.5%. Over 7 years = ₹0.77–1.12 Cr. Requires CSIR-IICT MOU as anchor document. Slow (6–9 months) so file immediately in parallel — do not wait for SIDBI sanction.Skip TDB (rejected: ₹1 Cr+ interest saving is too large to ignore)FILE IMMEDIATELY
Sep 2026BCR credits — register baseline with Puro.earth before commissioningCO₂ permanently fixed as PCC = 3,089 MT/yr. At $15–25/tCO₂ = ₹38–65L/yr. Cannot claim retroactively without pre-commissioning baseline documentation. One email to Puro.earth before Month 0 = ₹50+ Cr potential over 10 years.Skip BCR credits (rejected: zero-cost action with enormous upside; only risk is forgetting to do it)ACTION THIS WEEK
— Add new decisions below —
DateDecisionRationaleAlternatives rejected
Financing Application Tracker
SchemeSourceAmountRateApplied?StatusNext actionETA
SIDBI SMILESIDBI Hyderabad₹13.65 Cr10.5%NOT YETPrepare DPR v17 + CMA dataSubmit DPR package to SIDBI Hyd branchMonth −2
CGSS guaranteeNCGTC (via SIDBI)80% of loan0.5%/yr feeNOT YETApplied via lending bank simultaneouslyFile with SIDBI applicationMonth −2
SIDBI 4ESIDBI₹2–3 Cr7.5–8.5%NOT YETGreen assets: Solar, ETP, MVR, THUInclude green asset list in SIDBI applicationMonth −2
TDB LoanTechnology Development Board (DST)₹2–3 Cr5%NOT YETNeed CSIR-IICT MOU first1. Sign CSIR-IICT MOU. 2. File TDB application at dst.gov.in/tdbMonth −3 (parallel)
NABARD Agro-ProcessingNABARD₹3–5 Cr8–9%EXPLORERural location + agro-waste processing qualifiesContact NABARD District Development Manager, WanaparthyMonth −2
IREDA BiomassIREDA₹1–2 Cr8.5–9%EXPLORETHU + biomass combustion component qualifiesContact IREDA Hyderabad regional officeMonth −2
Udyam MSMEudyamregistration.gov.inNOT YET30-minute processRegister immediately — needed for SIDBI + CGSSTHIS WEEK
ECGC Export InsuranceECGC90% cover0.5–1%NOT YETRegister before first exportRegister at Month 10 before first export shipmentMonth 10
Interest Equalisation SchemeRBI (via lending bank)−2–3% subvention5–7% effectiveNOT YETExport packing credit; activate at bankActivate when first export order receivedMonth 12
80-IAC Tax HolidayIncome Tax (DPIIT)3 yr exemption100% ITNOT YETFile after first ITRFile at CA after first year of operationsMonth 24
Puro.earth BCR creditsPuro.earth voluntary market₹38–65L/yrUpsideNOT YETSend project description email for baseline documentationContact Puro.earth this week — before commissioningTHIS WEEK
RoDTEPDGFT0.5–1.5% FOBCash refundNOT YETRegister on DGFT portal at first shipping billMonth 12Month 12
— Add new scheme rows below —
Scheme nameSourceAmountRateApplied?StatusNext actionETA
PhaseMilestoneTarget dateOwnerStatusNotes
▶ PRE-CLOSE (Month −6 to 0)
Pre-closeUdyam MSME registrationThis weekPromoterOPEN30 mins at udyamregistration.gov.in
Pre-closeContact Puro.earth — BCR baseline documentationThis weekPromoterOPENSend project description email — cannot claim BCR retroactively
Pre-closeTSSPDCL 500 kW feasibility letter — Kothakota siteMonth −4PromoterOPENVisit Wanaparthy TSSPDCL office; written feasibility required before land purchase
Pre-closeCSIR-IICT MOU signedMonth −3PromoterOPENNeeded for TDB application anchor document
Pre-closeSIDBI + CGSS + TDB applications filedMonth −3Promoter + CAOPENDPR v17 + CMA data + Udyam + DPIIT cert + land docs package
Pre-closePlant manager recruitedMonth −1PromoterOPEN15+ yr chemical plant exp; must be on-site before equipment arrives; CTC ₹18–24L
Pre-closeTSPCB CTE application filedMonth −3Plant Manager + consultantOPEN6–9 month timeline; file early
Pre-closeKothakota land registered (title clear + patta)Month 0Promoter + advocateOPENDharani portal verification + advocate search mandatory before registration
▶ CIVIL + PROCUREMENT (Month 0–6)
CivilFinancial close — equity infused + bank drawdownMonth 0Promoter + bankOPENSIDBI sanction → drawdown → site mobilisation
CivilPMC / project manager appointedMonth 0PromoterOPENCommissioning consultant engaged simultaneously (PDIL or private ChemE; ₹3–5L/month for 6 months)
CivilLong lead-time POs placed — spray dryers, MVR, furnace+THUMonth 0–1Plant Manager + PromoterOPENSpray dryers: 12–16 week delivery · MVR: 14–18 weeks · Furnace+THU: 10–12 weeks
CivilCivil construction complete (all buildings)Month 3PMCOPENProcess bldg + THU room + warehouse + ETP + accommodation simultaneously
CivilDISCOM HT connection liveMonth 4PMC + TSSPDCLOPENSimultaneous with civil; 3–4 month DISCOM process
▶ ERECTION + COMMISSIONING (Month 5–12)
ErectionAll equipment installed + mechanical completionMonth 8Plant Manager + PMCOPENMechanical completion punch list; PLC panels installed; piping hydro-tested
Pre-commCEMS certified by TSPCBMonth 9Plant ManagerOPENMandatory before commercial operations; TSPCB inspector signs off
Pre-commFSSAI central licence application filedMonth 10PromoterOPEN12–18 month clock starts here; do NOT defer — dental revenue at Year 3 requires this
Pre-commFirst trial customer samples sent (SE Asia PS broker + 2 Indian rubber)Month 10–11Promoter + QC techOPENCOA with BET/PSD data; trial run product only; 3–4 week buyer approval cycle
CommissionFirst commercial batch — PS + PCCMonth 12Plant ManagerOPENFirst invoices; first export FCL to SE Asia; IES packing credit activated
▶ RAMP-UP + OPTIMISATION (Month 12–36)
RampHDS qualification samples — Apollo, MRF, CeatMonth 13–15Promoter + QC techOPEN3–6 month approval cycle; if pass, PS price ₹45–47/kg from Month 18
RampHDS qualification — Apollo/MRF/Ceat approvedMonth 18Promoter + QC techOPENv17: full 20 TPD PS from Day 1 — no Phase 1B capacity expansion needed; focus on grade upgrade to ₹72/kg HDS
OptimiseNaOH recovery ≥ 85% achievedMonth 18–24Plant Manager + CSIR-IICTOPENEach 1% improvement = ₹0.72 Cr/yr saving at v17 scale. Target: 82% → 86–88% via draft-tube optimisation
OptimiseFSSAI E551 certified — dental/food PS revenue liveMonth 28–30PromoterOPENPS price: ₹26 → ₹90–95/kg; Colgate/HUL/Dabur offtake pipeline
— Add milestones below —
PhaseMilestoneTarget dateOwnerStatusNotes
DocumentPurposeDue / File byFiled?File referenceRenewal
▶ COMPANY + COMPLIANCE
Certificate of Incorporation (CIN)Company identityDONE ✓DONEU35106TS2026PTC210706
DPIIT Startup RecognitionStartup benefits, CGSS eligibilityDONE ✓DONEDPIIT: 246192Annual renewal check
Udyam MSME RegistrationCGSS, SIDBI, CGTMSE eligibilityThis weekOPENAnnual update if turnover/investment changes
IEC (Import Export Code)All exports; LC discountingMonth −3OPENNo renewal — lifetime code
GST Registration (GSTIN)Billing, input creditMonth −2 (before billing)OPENAnnual returns; monthly GSTR-3B
Factory Licence (Factories Act)Legally operate factoryMonth 10 (before commissioning)OPENAnnual renewal
▶ ENVIRONMENTAL + SAFETY
TSPCB CTE (Consent to Establish)Permission to constructMonth −3FILE NOW5-year validity
TSPCB CTO (Consent to Operate)Permission to run commerciallyMonth 10–11OPENAnnual renewal
CEMS Certification (TSPCB)Continuous emission monitoring sign-offMonth 9OPENAnnual calibration
Fire NOC (District Fire Officer)THU oil + chemical storageMonth 11OPENAnnual renewal
ZLD compliance certificateTSPCB zero liquid dischargeAt CTOOPENWith annual CTO renewal
▶ FOOD / QUALITY CERTIFICATIONS
FSSAI Central Licence (E551 — food grade PS)Dental/food PS sales; ₹90–95/kg priceMonth 10 (file; 12–18M cycle)CRITICAL — CANNOT DEFERAnnual renewal
IS 6579 (Precipitated Silica General)BIS quality mark for domestic PS salesMonth 14–18OPEN2-year certification
ISO 9001 QMS CertificationExport credibility; mandatory for institutional buyersMonth 15OPEN3-year; annual surveillance audit
REACH Pre-registration (EU only)EU export; not required for SE Asia/MEYear 2 if EU export plannedDEFER
▶ FINANCING DOCUMENTS
DPR v17 (bank submission version)SIDBI + TDB applicationMonth −3IN PROGRESSfluxara-master-model.html (live)Update with each RFQ received
CMA Data (3-year projections — banker format)Bank sanction requirementMonth −3OPEN — CA to prepareAligned with DPR v17
Puro.earth BCR baseline documentationPre-commissioning baseline for CO₂ fixation creditsThis weekSEND EMAIL NOWOne-time baseline; keep records
— Add document rows below —
Document namePurposeDue dateFiled?ReferenceRenewal
RiskProbabilityImpactTriggerMitigationOwnerStatus
NaOH recovery below 80% at commissioningMediumHigh — +₹1 Cr/yr OPEX per 1% below 80%First causticisation batch recovery <80%CSIR-IICT lab trial before full commissioning; draft-tube causticiser already spec'd; 82% is conservative basePlant Manager + CSIR-IICTMONITOR
DISCOM does not sanction 500 kW at Kothakota siteLow-MediumHigh — plant cannot run without powerWritten refusal or >24-month wait from TSSPDCLGet written feasibility letter BEFORE land purchase; alternative: DG-only for 6 months + solar; or identify backup site near 33/11 kV sub-stationPromoterCRITICAL — GET LETTER FIRST
SIDBI / TDB sanction delayed >9 monthsMediumHigh — delays financial close and construction startSanction not received by Month −1Apply to 2 banks simultaneously (SIDBI + SBI or Canara). CGSS guarantee makes any bank more willing. TDB is parallel, not critical path — SIDBI alone is sufficient to start.Promoter + CAMONITOR
Spray dryer or MVR delivery delayed >4 weeksMediumMedium — critical path items; delays commissioningVendor confirms delay at Month 3 or laterOrder at Month 0 (immediate). Performance bond / advance linked to delivery date. Identify alternative vendor at RFQ stage.Plant Manager + PMCMONITOR AT PO STAGE
CTAB supply disruption (imported, 4-week lead time)MediumMedium — HDS grade production stops; revert to standardSupplier quotes >6-week lead timeMinimum 3-month buffer stock maintained. 2 import supplier relationships (China + Europe). CTAB only needed for HDS grade — standard grade unaffected.Plant ManagerMONITOR
SE Asia buyer rejects initial PS quality batchLow-MediumMedium — delays first export revenueCOA rejected or BET <130 m²/g on first batchSend trial samples from commissioning runs before booking FCL. Back up with 2–3 broker relationships. Standard PS is commodity — alternative buyers available within 2 weeks.Promoter + QC techMONITOR
Plant Manager resigns in first yearLowHigh — operational continuity risk at remote sitePM resignation notice receivedCompetitive CTC (₹22L) + performance bonus. On-site housing (retention anchor). 6-month notice clause in contract. Succession: promote senior operator + call commissioning consultant for 2-month bridge.PromoterMITIGATE AT HIRE
NaOH price spike +30%Low-MediumLow — sensitivity analysis shows EBITDA stays ₹35+ Cr at Y4+ even at NaOH +30%NaOH 48% lye exceeds ₹23,700/MTLong-term supply agreements with Grasim/DCW. NaOH recovery improvement from 82% → 87% partially offsets price increase. Price passed through to customers (export PS is spot-priced).Promoter (procurement)MONITOR
TSPCB CTO delayed beyond Month 11LowLow-Medium — delays commercial production startCTO not received by Month 11File CTE at Month −3 (leave full 14-month buffer). CEMS installation at Month 8 (leave 3 months for certification). Use consultant who knows TSPCB Wanaparthy district officials.Plant Manager + consultantMONITOR
— Add new risks below —
Risk descriptionProbabilityImpactTriggerMitigationOwnerStatus
Key Vendors — Equipment
RoleCompanyLocationContactStatus
Furnace 20 TPDThermax Bioenergy / Raj InternationalRajkotTBD — RFQ pendingRFQ OPEN
THU 3.5 MMkcal/hrForbes MarshallPuneTBD — RFQ pendingRFQ OPEN
Spray dryers ×2Raj Process EquipmentsPuneTBD — RFQ pendingRFQ OPEN
MVR evaporatorIPEC (Indian Process Equipment Corp)PuneTBD — RFQ pendingRFQ OPEN
Filter presses ×2Star Filter Press / Hydro PressGujarat/RajkotTBD — RFQ pendingRFQ OPEN
Leach reactors ×3Hydro Air EngineersHyderabadTBD — RFQ pendingRFQ OPEN
PCC hydrocyclonesKrebs Engineers IndiaVadodaraTBD — RFQ pendingRFQ OPEN
ETP + ZLD 25 KLDThermax Enviro / Enviro LabsHyderabadTBD — RFQ pendingRFQ OPEN
QC Lab (BET/PSD/XRF)Quantachrome India / Malvern-PanalyticalIndiaTBDRFQ OPEN
Financing + Institutional
RoleOrganisationContact personPhone / EmailStatus
Primary lender (SIDBI)SIDBI HyderabadTBD — visit branchOPEN
TDB applicationTechnology Development Board, DSTTBDdst.gov.in/tdbOPEN
CSIR-IICT MOUCSIR-IICT HyderabadTBD — contact Director's officeiict.res.inOPEN
Process advisoryCSIR-IICT / IIT Hyderabad ChemETBDOPEN
Commissioning consultantPDIL or private ChemETBD — advertise/headhuntHIRE MONTH −1
Plant Manager (critical hire)Own payrollTBD — Naukri / HeadHunters IndiaHIRE MONTH −1
BCR creditsPuro.earthproject@puro.earth (approx)puro.earthCONTACT THIS WEEK
ECGC export insuranceECGCTBD — Hyderabad officeecgc.inMONTH 10
Government / Regulatory
OfficePurposeContactNotes
TSPCB — Wanaparthy DistrictCTE, CTO, annual returnsTBD — visit district officeFile CTE at Month −3
TSSPDCL — Wanaparthy Division500 kW HT connection feasibilityTBD — Wanaparthy officeGet written feasibility BEFORE land purchase
DGFT — HyderabadIEC + RoDTEP claimsdgft.gov.inIEC: 2-3 days, ₹500 fee
District Fire Office — WanaparthyFire NOC for THU oil storageTBDFile at Month 10 with factory licence
FSSAI Central LicencingE551 food grade PSfssai.gov.inFile Month 10; 12–18 month cycle
Export / Customer Pipeline
Customer typeCompanyGradeStatusNotes
SE Asia broker (PS)TBD — Bangkok / JakartaStandard PS ₹42/kgIDENTIFY MONTH 1Commodity broker; 1 COA + 1 trial batch = approved
Indian rubber compounderTBD — GCC / TelanganaStandard PSIDENTIFY MONTH 1Domestic spot market; backup for export
Indian tyre OEM (HDS)Apollo Tyres / MRF / CeatHDS PS ₹47/kgSAMPLES MONTH 11–136–12 month qualification; CTAB ≥175 mg/g required
Sealant grade PCCPidilite / Sika / HenkelSealant PCC ₹26/kgSAMPLES MONTH 14d50 0.7 µm · stearic coated; 4–6 month approval
Coatings PCCAsian Paints / Berger / NerolacBulk PCC ₹10/kgSAMPLES MONTH 122 µm d50, brightness ≥97; fastest approval
Dental PS (FSSAI)Colgate / HUL / DaburDental PS ₹90–95/kgYEAR 3FSSAI E551 required; file Month 10
This is the authoritative source of truth for all project assumptions. See fluxara-master-model.html for the interactive financial model. Update both when any assumption changes. Last sync: Sept 2026 (DPR v17).
Locked Process Constants (Do Not Change Without Full Revision)
ParameterValueSource
Phase 1A RHA processed/day15.032 MT/day11.432 purchased + 3.600 bonus
PS produced / day (v17)20 MT/day = 6,600 MT/yrEngineering calc
Nano-PCC / day (v17)30 MT/day = 9,900 MT/yrEngineering calc
CaO consumed / day (v17)20.5 MT/dayv17 (20 TPD PS scale)
NaOH gross circuit~24.3 MT/dayEmpirical causticisation circuit
NaOH recovery rate82% (target 86–88% Y2)Lab validation required at commissioning
NaOH fresh makeup / day4.375 MT/day = 9.114 MT/day as 48% lye24.3 × (1−0.82)
Operating days / year330Locked
Thermal surplus (with MVR)21 GJ/dayv17: 21 GJ/day (v16 was 83 GJ/day at lower capacity)
CO₂ surplus (not in base)15.69 MT/day vented; 1.5 MT/day capturableUpside only
RHA SiO₂ content92% amorphous (<700°C)Critical — furnace temp ≤700°C hard limit
SiO₂ extraction efficiency88%Lab validation required
Price Assumptions — Current (DPR v17, Sept 2026)
ItemPriceNotes
NaOH 48% lye₹18,240/MT= ₹38,000/MT 100% NaOH equiv
CaO quicklime₹6,000/MTPiduguralla AP ≥85% purity; ~190 km from Kothakota
Rice husk₹5,500/MTRange ₹4,500–6,500 seasonal ±15%
Purchased RHA₹750/MTMin 90% SiO₂ contract clause
CTAB (imported)₹1,80,000/MTHighest supply risk; 4-week buffer mandatory
Stearic acid₹1,20,000/MTDomestic vegetable-based
Electricity₹7/kWhNet of solar credit
Standard PS (export FOB)₹42/kgSE Asia / ME rubber compounders; commodity grade
HDS PS (export FOB)₹72/kgApollo/MRF/Ceat qualified; from Month 18
Dental PS (export/domestic)₹144/kgFSSAI E551 required; from Year 3 (Month 36)
Bulk PCC₹10/kgCoatings, paper; domestic
Sealant PCC₹26/kgStearic coated, d50 0.7 µm; Pidilite/Sika
Desilicated residue₹900/MTBrick kilns; 2.862 MT/day
This tab tracks all open action items. Resolve each row by updating status. Items stay here even when resolved — use Status column to mark DONE.
#ActionOwnerDuePriorityStatusNotes
1Register Udyam MSMEPromoterThis weekP0 NOWOPEN30 min · udyamregistration.gov.in · need for SIDBI + CGSS
2Email Puro.earth — BCR baseline documentationPromoterThis weekP0 NOWOPENCannot claim CO₂ fixation credits retroactively; one email = ₹50+ Cr potential
3Get TSSPDCL 500 kW feasibility letter — KothakotaPromoterBefore land purchaseP0 CRITICALOPENVisit Wanaparthy TSSPDCL office; written letter; do NOT buy land without this
4Shortlist 3 vendors for 6 priority RFQ itemsPromoter + PM (when hired)Month −3P1OPENSpray dryers · Furnace+THU · MVR · ETP+ZLD · Filter presses · PCC hydrocyclones — RFQs lock ±10% accuracy on TPC
5Sign CSIR-IICT MOUPromoterMonth −3P1OPENAnchor document for TDB application; contact Director's office at iict.res.in
6File TSPCB CTE applicationConsultant (to hire)Month −3P1OPEN6–9 month timeline; delay in filing = delay in commissioning
7File SIDBI SMILE + CGSS applicationPromoter + CAMonth −3P1OPENNeed: DPR v17 (done) · CMA data (CA to prepare) · Udyam cert · DPIIT cert · land docs
8File TDB loan application in parallelPromoter + CAMonth −3P1OPEN5% rate; slow but worth it. File at dst.gov.in/tdb simultaneously with SIDBI
9Advertise / headhunt Plant ManagerPromoterMonth −2P1OPEN15+ yr chemical plant exp · ₹18–24L CTC · must be on-site before equipment arrives (Month 0) · Naukri.com / HeadHunters India
10Verify IEC registration (if not done)PromoterMonth −2P1OPEN₹500 at DGFT portal; 2 days; needed for all export from Day 1
11Engage SE Asia PS export brokerPromoterMonth 1P2OPENBangkok / Jakarta rubber chemicals distributor; standard PS commodity buyer
12Commission accommodation block civilPMCMonth 3P2OPEN₹44L; PM house + 4 staff quarters + canteen; simultaneous with process building civil
— Add new open items below —
#Action itemOwnerDuePriorityStatusNotes