Pre-close
M−6→M0: Land · CTE · bank DPR · Plant Manager hire
Mobilise
M0→M1: Financial close · site mobilisation · long-lead POs
Civil
M1→M3: Process building · THU room · ETP · accommodation
Procure
M3→M6: Equipment delivery + erection begins
Erect
M5→M8: All equipment installed · piping · cabling · PLC panels
Pre-comm
M8→M10: CEMS cert · CTO application · trials · FSSAI filed
Commission
M10→M12: First PS batch · first PCC · first invoice
Ramp-up
M12→M18: 60→75% · first export FCL · HDS samples · 20 TPD from Day 1
Optimise
M18→M36: HDS qual · sealant PCC · FSSAI E551 dental grade